Claremont Football Club is quickly looking more and more like a Stadium than a construction site with all the seating installed with the colours of the Claremont Tigers shining bright. The Façade is a timely process but is being installed in areas where the scaffold has been dismantled with the window and cladding installation following closely behind.
The Roof is 80% complete & all finishing contractors are on site amongst other trades installing tiles, applying paint, measuring joinery and installing floor finishes.
The Car park is very close to being complete with Kerbing and wheel stops 100% installed, all that’s left is a few minor services, a clean and some line marking.